Decision details

Contract Award for External Refurbishment at 19-22, 35-38, 41-44, 55-58, 158-161, 167-170, 189-192 and 198-201 Potters Field

Decision Maker: Cabinet

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Decision:

RESOLVED that:

 

A     The most advantageous tender in consideration of price and quality combined as submitted by Contractor A, be accepted in the sum of £322,425.00 for the delivery of the external refurbishment of eight blocks, subject to contract and Leaseholder Consultation.

Report author: Andrew Murray

Publication date: 03/12/2021

Date of decision: 02/12/2021

Decided at meeting: 02/12/2021 - Cabinet

Effective from: 11/12/2021

Accompanying Documents: