Capital Programme, Quarter 3 Finance Report 2022/23

Decision Maker: Cabinet

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

RESOLVED that Cabinet:

 

A    Noted the progress and forecasts in the delivery of the Council’s Housing Capital Programme (HCP) as at Quarter 3 2022/23 as follows:

 

             i)        The current budget is £24.770 million, including £2.762 million carried forward from 2021/22. The projected outturn at Quarter 3 is £27.078 million as set out in Appendix 1 to the report.

 

B    Noted the progress in the delivery of the Council’s Non-Housing Capital Programme (NHCP) as at Quarter 3 2022/23 as follows:

 

             i)        The current budget is £19.325 million, including £4.066 million carried forward from 2021/22. The projected outturn at Quarter 3 is £34.800 million as set out in Appendix 2 to the report.

 

C    Approved the inclusion in the NHCP budget of an additional £71,000 for the installation of CCTV at various underpasses. Expenditure is to be fully financed from external grant.

Report author: Simon Freeman

Publication date: 24/03/2023

Date of decision: 23/03/2023

Decided at meeting: 23/03/2023 - Cabinet