Appointment of Contractor for Council House Building Programme Scheme - Staple Tye

Decision Maker: Cabinet

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Decision:

RESOLVED that delegated authority be given to the Chief Executive, in consultation with the Leader of the Council, to proceed to the final construction phase of the development and agree the procurement and appointment of a main contractor for the of the Staple Tye Renewal Scheme (Parnell Road, Perry Road & the Staple Tye Depot Sites), as part of the Council House Building Programme, within the financial budget set in the approved Harlow Council Capital Programme 2024/25 - 2027/28.

Report author: James Gardner

Publication date: 18/06/2024

Date of decision: 13/06/2024

Decided at meeting: 13/06/2024 - Cabinet

Effective from: 26/06/2024