Decision Maker: Cabinet
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
RESOLVED that Cabinet acknowledges the projected outturn position set out in section three of the Appendix to the report submitted for the third quarter (October – December) of 2014/15 as follows:
i. A projected under-spend on controllable budgets of £252,000, representing -0.38 per cent of the gross General Fund budget.
ii. A total projected under-spend of £300,000 representing -0.45 per cent of the gross General Fund budget.
iii. The Council performed on or above target for 42 out of 48 (86 per cent) of performance indicators.
Publication date: 30/03/2015
Date of decision: 26/03/2015
Decided at meeting: 26/03/2015 - Cabinet