Decision Maker: Cabinet
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: No
RESOLVED that Cabinet:
A Notes the outturn of the Council’s Housing and Non Housing Capital Programmes as at 31 March 2014 detailed as follows:
(i) Housing Capital Programme expenditure of £24,846,000 against an approved revised budget of £26,297,000.
(ii) Non Housing Capital Programme expenditure of £1,398,000 against an approved revised budget of £2,734,000.
B Approves the carryover of Housing Capital programme schemes to 2014/15 of £1,101,000 to meet capital commitments.
C Approves the carryover of Non Housing Capital Programme schemes to 2014/15 of £781,000 to meet capital commitments.
D Recognises the operational performance which has been achieved across all Council services during 2013/14.
Publication date: 18/07/2014
Date of decision: 17/07/2014
Decided at meeting: 17/07/2014 - Cabinet