Decision Maker: Cabinet
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
RESOLVED that Cabinet:
A Noted the progress in the delivery of the Council’s Housing and Non Housing Capital Programmes as at Quarter 1 (30 June 2019) as follows:
i) Housing Capital Programme – forecast outturn £23,743,000 (original estimate £24,044,000).
ii) Non Housing Capital Programme – forecast outturn £15,618,000 (original estimate £11,156,000). The outturn includes a new budget for work to Enterprise Zone Plot H “Modus” approved by Cabinet on 20 June 2019 with a £7.2 million budget as set out in Annex A14 to the report.
B Approved the revised Housing Capital Programme for 2019/20 outlined in paragraph 19 to the report.
Report author: Simon Freeman
Publication date: 13/09/2019
Date of decision: 12/09/2019
Decided at meeting: 12/09/2019 - Cabinet