Decision Maker: Deputy Leader and Portfolio Holder for Housing
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
RESOLVED that The most economically advantageous tender submitted by Contractor A who is Chas Berger Ltd (company registration number 00359611), is accepted in the sum of £461,022.18 for the delivery of internal and external refurbishment and fire safety works to 1 – 10 The Friars based on a twenty-week working programme and four week lead in period “subject to contract and leaseholder consultation”.
To enable the Council to enter into a formal contract for refurbishment and fire safety works in accordance with Contracts Standing Orders.
Withdraw the refurbishment work
i) Withdrawal of the works will result in further deterioration and failure of non serviceable elements of the building structure, communal areas and exterior of the block.
ii) To mitigate this, the block must be maintained to ensure it is weathertight and therefore habitable, free from defect, disrepair in compliance with the decent home’s standard.
iii) Recommendations from the fire risk assessment won’t be addressed thus Harlow Council will not be meeting their legal obligations to keep residents safe if withdrawn.
iv) Additionally, Harlow Council will not be adhering to the following legal and duty of care requirements as Landlord:
· Landlord and Tenant Act 1985 (Section 9 &11)
· Homes (Fitness for Human Habitation) Act 2018
· Housing Act 2004 (The Housing Health and Safety Rating System (HHSRS))
· The Regulatory Reform (Fire Safety) Order 2005
· Building Safety Act 2022
· The Fire Safety (England) Regulations 2022
· Decent home standard
Reduce the package/partially undertake the work
i) Works can be undertaken separately or only partially but there is a risk that this approach would leave Harlow Council open to litigation due to failure to adhere to the legislation detailed above where health and safety issues, failing or deteriorated elements of the building are not addressed.
ii) It is more cost effective to package works together to benefit from the economy of scale and to reduce duplicating or increasing costs that form a package of refurbishment works such as site set up, welfare, contractor prelims, management costs etc. that would be attracted if the works weren’t undertaken collectively.
Use alternative contractor (B, C or D)
i) The Council award contracts based on the most advantageous tender. We consider, not only price but also quality as follows:
· evidence of qualifications, experience, method statements and risk management
· how proposed procurements could make local improvements and how these could be delivered via the procurement process
· how what is being procured may improve the economic, social and environmental wellbeing of Harlow and the surrounding areas
equality, diversity and sustainability issues
Publication date: 10/04/2024
Date of decision: 08/04/2024
Effective from: 16/04/2024
Accompanying Documents: