HTS (Property and Environment) Limited Contract Awards 2017/18 - Phase 2

Decision Maker: Cabinet

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Decision:

A     The following Phase 2 Business Cases were awarded to HTS (Property and Environment) Limited subject to terms and conditions, and that separate contracts are entered into for each activity not exceeding the values set out in the table below:

 

a)

Communal Boilers

£1,912,000

b)

Energy Efficiency

£188,000

c)

Garages

£500,000

TOTAL

£2,600,000

 

Report author: Andrew Murray

Publication date: 15/09/2017

Date of decision: 14/09/2017

Decided at meeting: 14/09/2017 - Cabinet

Effective from: 23/09/2017