Decision details

Contract Award for Refurbishment Works to Temporary Accommodation

Decision Maker: Cabinet

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Decision:

RESOLVED that Cabinet:

 

A     Accepted the most advantageous tender assessed against the criteria included in the tender documents, submitted by Contractor A, in the sum of £356,261 subject to contract and confirmation of Planning Consent.

Report author: Andrew Murray

Publication date: 08/12/2017

Date of decision: 07/12/2017

Decided at meeting: 07/12/2017 - Cabinet

Effective from: 16/12/2017

Accompanying Documents: