50 Referral from Cabinet - Capital Programmes 2019/20 - 2021/22 PDF 376 KB
Cabinet recommended to Full Council that:
Housing Capital Programme
i) The Housing Capital Programme 2019/20 revised outturn of £23,005,000, as set out in Table 2 of the report is noted.
ii) The Housing Capital programme 2020/21 of £27,739,000, as set out in Table 5 of the report is approved, including £10.2 million of external borrowing in 2020/21 and a further £8.7 million in the following two years to support building council homes. Total borrowing £18.9 million.
Non Housing Capital Programme
iii) The revised Non Housing Capital Programme 2019/20 of £13,738,000, as set out in Table 6 of the report is noted.
iv) The Non Housing Capital Programme for 2020/21 £11,048,000 including the Enterprise Zone (Modus), £5,363,000, and Elm Hatch £1,185,000, as set out in Table 10 of the report is approved.
v) External borrowing of £13.8 million is approved to support the Non Housing Capital Programme in 2020/21 and a further £10.2 million in respect of the Housing Capital Programme.
Minutes:
Cabinet recommended to Full Council that:
Housing Capital Programmes
A The Housing Capital Programme 2019/20 revised outturn of £23,005,000, as set out in Table 2 of the report is noted.
B The Housing Capital programme 2020/21 of £27,739,000, as set out in Table 5 of the report is approved, including £10.2 million of external borrowing in 2020/21 and a further £8.7 million in the following two years to support building council homes. Total borrowing £18.9 million.
Non Housing Capital Programme
C The revised Non Housing Capital Programme 2019/20 of £13,738,000, as set out in Table 6 of the report is noted.
D The Non Housing Capital Programme for 2020/21 £11,048,000 including the Enterprise Zone (Modus), £5,363,000, and Elm Hatch £1,185,000, as set out in Table 10 of the report is approved.
E External borrowing of £13.8 million is approved to support the Non Housing Capital Programme in 2020/21 and a further £10.2 million in respect of the Housing Capital Programme.
Proposed by Councillor Mark Ingall (seconded by Councillor Mike Danvers) it was:
RESOLVED that the recommendations above be approved.
110 Capital Programmes 2019/20 - 2021/22 PDF 376 KB
Decision:
RESOLVED that Cabinet recommends to Full Council that:
Housing Capital Programme
A The Housing Capital Programme 2019/20 revised outturn of £23,005,000, as set out in Table 2 of the report is noted.
B The Housing Capital programme 2020/21 of £27,739,000, as set out in Table 5 of the report is approved, including £10.2 million of external borrowing in 2020/21 and a further £8.7 million in the following two years to support building council homes. Total borrowing £18.9 million.
Non Housing Capital Programme
C The revised Non Housing Capital Programme 2019/20 of £13,738,000, as set out in Table 6 of the report is noted.
D The Non Housing Capital Programme for 2020/21 £11,048,000 including the Enterprise Zone (Modus), £5,363,000, and Elm Hatch £1,185,000, as set out in Table 10 of the report is approved.
E External borrowing of £13.8 million is approved to support the Non Housing Capital Programme in 2020/21 and a further £10.2 million in respect of the Housing Capital Programme.
Minutes:
The Cabinet received a report on the outturn for 2019/20 and proposed programmes for 2020/21.
Proposed by Councillor Mike Danvers (seconded by Councillor Mark Ingall) it was:
RESOLVED that Cabinet recommends to Full Council that:
Housing Capital Programme
A The Housing Capital Programme 2019/20 revised outturn of £23,005,000, as set out in Table 2 of the report is noted.
B The Housing Capital programme 2020/21 of £27,739,000, as set out in Table 5 of the report is approved, including £10.2 million of external borrowing in 2020/21 and a further £8.7 million in the following two years to support building council homes. Total borrowing £18.9 million.
Non Housing Capital Programme
C The revised Non Housing Capital Programme 2019/20 of £13,738,000, as set out in Table 6 of the report is noted.
D The Non Housing Capital Programme for 2020/21 £11,048,000 including the Enterprise Zone (Modus), £5,363,000, and Elm Hatch £1,185,000, as set out in Table 10 of the report is approved.
E External borrowing of £13.8 million is approved to support the Non Housing Capital Programme in 2020/21 and a further £10.2 million in respect of the Housing Capital Programme.