146 Capital Programmes, Quarter 3 Finance Report 2017/18 PDF 523 KB
Decision:
RESOLVED that Cabinet:
A Noted the progress in the delivery of the Council’s Housing and Non-Housing Capital Programmes as at Period 9 (31 December 2017) as follows:
i) Housing Capital Programme – forecast outturn of £14,098,000 (original estimate £18,530,000).
ii) Non-Housing Capital Programme – a forecast outturn of £8,948,000 (original estimate £5,425,000).
B Approved the inclusion in the Non-Housing Capital Programme of a business case for:
i) Works to alleviate flooding in the Sumners Area through infrastructure and drainage works (£58,000). This is fully grant funded by the County Council from the Community Flood Improvement Fund.
Minutes:
Cabinet received a report which provided an update on the Council’s Housing and Non-Housing Capital Programmes and sought approval for one business case.
Proposed by Councillor Mike Danvers (seconded by Councillor Mark Ingall) it was:
RESOLVED that Cabinet:
A Noted the progress in the delivery of the Council’s Housing and Non-Housing Capital Programmes as at Period 9 (31 December 2017) as follows:
i) Housing Capital Programme – forecast outturn of £14,098,000 (original estimate £18,530,000).
ii) Non-Housing Capital Programme – a forecast outturn of £8,948,000 (original estimate £5,425,000).
B Approved the inclusion in the Non-Housing Capital Programme of a business case for:
i) Works to alleviate flooding in the Sumners Area through infrastructure and drainage works (£58,000). This is fully grant funded by the County Council from the Community Flood Improvement Fund.