Venue: Council Chamber, Civic Centre
Contact: Email: governance@harlow.gov.uk
Webcast: View the webcast
No. | Item |
---|---|
Webcast Introduction The Chair will read out the following statement:
“This meeting is being webcast live to our website (https://harlow.public-i.tv/core/portal/home) and will be available for repeated viewing after the meeting has ended.
By continuing to attend this meeting, you are consenting to being filmed and to appearing in the webcast.
I would like to remind all those participating in the meeting to use their microphones when they speak, and to turn them off once they have finished talking.” Additional documents: |
|
Apologies for absence Additional documents: |
|
Declarations of Interest Councillors’ declarations of interest (if any) in relation to any items on the agenda. Additional documents: |
|
To approve the minutes of the meetings held on 5 and 12 June. Additional documents: |
|
Matters Arising Any matters arising from the minutes of the previous meeting. Additional documents: |
|
Written Questions from the Public To receive any questions from members of the public in accordance with Rule 10 of the Council Procedure Rules. Additional documents: |
|
Written Questions from Councillors To receive any questions from Councillors in accordance with Rule 10 of the Council Procedure Rules. Additional documents: |
|
Communications from the Leader Additional documents: |
|
Petitions To consider any petitions that have been referred to the Cabinet under the Council’s Petition Scheme. Additional documents: |
|
Recent Relevant Decisions Taken by The Leader, Deputy or Portfolio Holder(s) There have not been any decisions taken by Portfolio Holders under delegated powers since the last meeting of the Cabinet. Additional documents: |
|
Building Harlow's Future - Delivery Update Additional documents:
Decision: RESOLVED that Cabinet noted:
A The progress of projects that are delivering the Building Harlow’s Future plan.
B The performance of key performance indicators for each Mission for May 2025 which demonstrate strong performance on majority of indicators.
C The financial position as of May (period 2) of 2025/26 financial year.
D The position of the strategic risk register to align with Building Harlow’s Future. |
|
Additional documents: Decision: RESOLVED that Cabinet:
A Noted the update on Local Government Reorganisation for Greater Essex.
B Endorsed Harlow Council’s continued participation with the production of the Five Unitary Business Case (formerly Business Case A) and the Business Case for Greater Essex (formerly Business Case B) recognising that a formal decision on the council’s position will be taken in September. |
|
Regulator for Social Housing - Update Additional documents: Decision: RESOLVED that Cabinet noted the progress being made and actions agreed with the Regulator of Social Housing to manage our ongoing social housing compliance responsibilities and the wider elements of the Safety and Quality standard, and to improve our performance in this area. |
|
Additional documents:
Decision: RESOLVED that Cabinet approved:
A The framework ‘Rebuild: Reimagine - establishing Harlow as a cultural capital’, attached as Appendix A to the report.
B The use of £55,000 from discretionary services fund to create a heritage and culture grant scheme. |
|
Child and Adult Safeguarding Policy Additional documents: Decision: RESOLVED that the revised and updated Child and Adult Safeguarding Policy covering the period 2025/26 – 2027/28, attached as Appendix A to the report, be approved. |
|
Outturn Report 2024/25 Additional documents:
Decision: RESOLVED that Cabinet:
A Endorsed the outturn position for 2024/25 of £0.261 million surplus, as set out within the report in respect for General Fund year ending 31 March 2025.
B Endorsed the outturn position for 2024/25 of £4.136 million surplus as set out within the report in respect for Housing Revenue Account year ending 31 March 2025.
C Endorsed the Non-Housing Capital Programme (NHCP) outturn for 2024/25 is £26.789 million and the Housing Capital Programme (HCP) outturn for 2024/25 is £44.444 million as set out in the report.
D Endorsed the Earmarked Reserves summary in Appendix E to the report.
E Endorsed that the £0.261 million from the General Fund surplus was contributed to the Neighbourhood Renewal Fund reserve for identified projects within the Neighbourhood Renewal Fund programme.
F Noted the Period 12 reprofiling into 2025/26 within the Non-Housing and Housing Capital Programmes included within Appendices C and D to the report.
G Noted the carry forward of resources from 2024/25 to 2025/26 as set out in Appendix F to the report. |
|
Delegation of Authority for the Grant of Commercial Leases Additional documents: Decision: RESOLVED that:
A Cabinet delegated authority to the Director for Facilities and Assets to agree terms and thereafter procure the legal completion of new commercial leases, subject to the Executive Director (Regeneration and Community Focus) being satisfied that:
i) the subject property isn’t required by the council over the duration of the proposed lease for operational purposes;
ii) the terms of the proposed lease are at or better then open market value;
iii) entering into the proposed lease would not reduce the retained capital value of the subject property; and
iv) entering into the proposed lease would not impede the council in delivering its policy objectives (for example its programme of town centre regeneration).
B Cabinet agreed the following financial limits for the grant of commercial leases:
i) Up to £150,000 total lease value – Approval by the Executive Director (Regeneration and Community Focus);
ii) From £150,000 - £500,000 - Approval by the Executive Director (Regeneration and Community Focus) in consultation with the relevant Portfolio Holder; and
iii) Above £500,000 – Approval by Cabinet. |
|
Energy Procurement Framework Renewal Additional documents: Decision: RESOLVED that Cabinet agreed:
A To extend the current contract with Inspired Energy for the procurement of gas and electricity via the Procurement for Housing framework from April 2026 to March 2028.
B That the contract extension also includes additional services for pre-payment bill validation and annual budget production. |
|
Council House Building Programme Annual Update Report Additional documents:
Decision: RESOLVED that Cabinet noted the report and progress achieved in delivering the Council House Building Programme (CHBP) in the previous 12 months. |
|
Communications from Committees/Working Groups/Parties and Panels Additional documents: |
|
Minutes of Panels/Working Groups To note the following draft minutes of Cabinet appointed bodies. Minutes remain draft until approved by the relevant body. Additional documents: |
|
Minutes of meeting Thursday, 19 June 2025 of Harlow Local Highways Panel Additional documents: |
|
Matters of Urgent Business Such other business which, in the opinion of the Chair, should be received as a matter of urgency by reason of special circumstances to be specified in the minutes. Additional documents: |
|
HTS Transformation Update Additional documents:
Decision: RESOLVED that Cabinet:
A Approved an increase in the repairs and maintenance budget of £1,456,964 which reflects the increased demand for day-to-day repairs and the numbers of empty homes that require works before being relet.