Issue - decisions

Fire Safety Works - Brenthall Tower 1-28, Brenthall Tower 29-56 and Stort Tower

25/03/2022 - Fire Safety Works - Brenthall Tower 1-28, Brenthall Tower 29-56 and Stort Tower

RESOLVED that:

 

A    The most advantageous tender in consideration of price and quality combined as submitted by Contractor B be accepted in the revised sum of £1,281,792.92 for the delivery of updated Fire Compartmentation between floors, in service duct and ventilation system, internal and front entrance fire doors programme, subject to contract and Leaseholder consultation.